Writing an office fit-out brief that designers and contractors can price
A fit-out brief is a pricing document before it is a design document. What to fix in writing, what to measure on site, and what to leave for the designer to solve.
Contents
This is for anyone about to take office space in the UAE or refit the space they already have: a business of ten people, a clinic's back office, a trading firm moving out of a serviced suite. It sets out what belongs in a fit-out brief so that two designers and two contractors can price the same thing, and so that the differences between their quotations mean something. The brief is not a mood board. It is a list of facts, constraints and decisions, with the remaining questions marked as questions.
Start with how people actually work, not a desk count
A single number, say forty staff, produces a generic floor plate and a quotation nobody can defend later. Break the headcount into teams and describe the week. Which teams are at their desks most days, which come in for two days and spend the rest at client sites, which need to sit together because they talk constantly, and which need distance because they are on calls. A sales team on the phone all afternoon and a finance team reconciling figures cannot share an open bench without a wall or some distance between them.
Write down the peak, not the average. If everyone is in on Monday, the pantry, the toilets, the meeting rooms and the lift lobby are sized for Monday. Note growth as a range with a date attached, and say whether the extra people should be accommodated by denser benches, a second shift of shared desks, or more floor area. Those are three different prices.
Then describe the work itself in plain terms: how many monitors per person, whether anyone handles large drawings or samples, whether staff eat at their desks, whether visitors are frequent and whether they should ever see the working floor. Include the awkward items early. A safe, a server cupboard, a printer that vents, a store for stock or archive boxes, a prayer space, a place for a delivery trolley to stop. These occupy area and carry services, and finding them late means moving walls that are already priced.
Rooms: meetings, calls and one door that closes
List rooms by purpose and capacity rather than by name. A room for eight with a screen and a table is a different proposition from a room for four with a writable wall and no video kit. State how many meetings run at once at the busiest hour, because that governs the count more honestly than a ratio of rooms to desks. Say which rooms need visual privacy, which need speech privacy, and which need both. Glass with a curtain gives one and not the other; a glazed partition needs attention at the head, the floor junction and the door seal before anyone can call it acoustically private.
Small rooms matter more than the large one. One or two single-occupancy rooms for video calls, plus a room with a door that closes for a difficult conversation, a medical call or a feed, will be used every day. Give them a light level someone can read a face by, a background that is not a corridor, and extract air that keeps them fresh with the door shut for an hour.
- For each room: purpose, seats, equipment, privacy needed (visual, speech, both), and whether it must be bookable.
- For each open area: teams, desks, monitors per desk, storage per person, and noise expectation.
- For each support space: pantry, print, store, comms cupboard, cleaner's cupboard, prayer space, first aid.
Storage is the item most often left vague. Say linear metres of shelving for files, whether archive is on site or off site, and whether personal storage is a pedestal at the desk or a locker near the door. Lockers only work if they are on the route people already walk.
The landlord's base build and its rules
Before any layout is drawn, collect the base build information from the landlord or building manager: the shell condition, floor loading, slab-to-soffit height, the position of incoming power and its capacity, chilled water or packaged cooling, drainage points, the fire alarm and sprinkler arrangement, and where fresh air comes from. Ask for drawings in a usable format and for the fit-out manual. Most buildings in Dubai and Abu Dhabi have one, and it governs more than owners expect.
Read it for the clauses that cost money. Permitted working hours and noisy-work windows. Lift access for materials and whether it must be booked and protected. Hoarding and signage requirements at the entrance. Restrictions on cutting the slab, on penetrations through the facade, on fixing to the soffit, on wet areas away from existing drainage. Whether the landlord's own contractor must do the fire alarm, sprinkler and BMS modifications. Insurance requirements, deposit conditions, and who signs off completion before the deposit returns. Approvals from the building and, where applicable, the authority may sit on the critical path longer than the joinery does.
Record what you find on site as well as on paper. Measure the clear height under the lowest duct, not the drawing dimension. Photograph the ceiling void with the tile lifted. Note where the sprinkler heads and detectors already sit, because relocating them is a package with its own approvals. Understanding the key people on an interior design and fit-out project helps here: the landlord's engineer, the building's approved specialist subcontractors and your own project lead all hold parts of the answer, and none of them holds all of it.
Mechanical and electrical constraints decide the ceiling
An office ceiling is a negotiation between ducts, sprinkler heads, detectors, speakers, luminaires and access panels. In a hot climate the cooling load is set by glass, occupancy and equipment, and the brief should state the equipment honestly: number of workstations, monitors, any local servers, the pantry appliances. If a corner suite faces west with unshaded glazing, say so, and expect the answer to involve diffuser positions and possibly blinds rather than more tonnage.
Ask for the electrical strategy in writing. Where the distribution board sits, whether floor boxes or desk-fed power are permitted, how data is distributed, where the comms cupboard is and whether it needs its own cooling. Decide who supplies and who installs the IT active equipment, the audio-visual kit, the access control and the cabling; split responsibilities are the commonest source of a gap between two quotations. Specify socket counts per desk and per meeting room as numbers, and give the AV requirement as a function: display size readable from the far seat, a camera that sees the whole table, a microphone that reaches the person at the end.
Lighting should be given as levels and qualities, not fixture names. A task level at the desk, a lower ambient level in circulation, glare control at screens, a colour temperature held consistent across the floor, and dimming or zoning so half the floor is not lit at full output for two people working late. The same logic that governs gypsum ceilings and layered lighting in a house applies in an office, with the added constraint that every dropped section must still allow access to dampers and valves.
Finishes standard, and what to leave open
Describe the standard by performance and location, then let the designer propose materials. Carpet tile or resilient flooring in the working area, and why: acoustics, replacement of stained tiles, trolley traffic. Hard flooring in the pantry with a slip rating and a drain if there is a sink run. Wall protection where trolleys turn. Cleanable surfaces at touch height. Ceiling absorption sufficient that a room of thirty people does not roar. State the maintenance reality: who cleans, how often, and whether a material that needs sealing every year is acceptable. Fire performance and reaction-to-fire classifications are not optional in a commercial building, and the brief should require documentation for every specified surface.
Then be explicit about what is fixed and what is open. Fixed: headcount, rooms and capacities, adjacency requirements, budget envelope, programme dates, landlord rules, the equipment schedule. Open: layout geometry, joinery design, colour and material palette, furniture selection within a stated allowance, lighting appearance. Designers price uncertainty badly. If a decision is genuinely undecided, mark it as an option with a date by which it will be resolved, rather than leaving a silence that each tenderer fills differently.
Phasing belongs in the same document. If the business keeps running, say which teams move first, what must stay live (server, reception, one meeting room), what noise is tolerable and when, and how dust is separated from occupied space. A handover in zones with temporary protection and a defined access route costs differently from a single empty-floor handover, and the difference should be visible in the price rather than discovered on site.
Before you send the brief out
- Walk the space with the building manager and a tape. Photograph the ceiling void, the riser, the incoming power and the drainage points. Note clear heights.
- Obtain the fit-out manual, base build drawings and the list of landlord-approved specialists, and attach them to the brief.
- Write the headcount table by team with attendance patterns and a growth range, then the room list with capacities and privacy requirements.
- Fix the equipment and IT schedule, and state who supplies and who installs each item.
- Set the finishes standard by performance, name the maintenance regime, and list what remains open with resolution dates.
- Issue the identical pack to every tenderer, ask for exclusions in writing, and hold a site visit on the same day for all of them.
Compare the returns line by line rather than on the total. Where one price includes sprinkler modifications and another excludes them, the cheaper number is not cheaper. Ask each tenderer to list the three items they consider least defined; the answers will show you where the brief is still thin, and repairing those pages before appointment is cheaper than repairing them after.